China: Chuxiong Cigarette Factory Completes the Work of Equipment Relocation

Chuxiong Cigarette Factory completed the Work of equipment relocation with the last machine entering the joint workshop in new factory on May 23. On May 12, soft pack production line shut down, and the relocation work began from May 14. On May 14, hard pack production line shut down, so the old plant of Chuxiong Cigarette Factory was closed completely.

The total location work was completed during 10 days. 15 sets of soft pack production line bean to do trial production in new plant. The hard pack production line will to do trial production soon after it was installed in the new plant. Cigarette manufacturing production line will to do trial production from the mid of July after all the equipment was installed and tested. The company will in normal production from July 1. Enditem